Our case studies

BETTY REDEVELOPMENT

PROJECT DESCRIPTION

The Betty existing infrastructure comprises three (3) platforms: one (1) Drilling and Production Platform (BEDP-A), a Separation and Liquid Handling Platform (SEP-A) and a Remote Vent Platform (BEV-A). BEDP-A and BEP-A are interconnected by a bridge whereas BEP-A and BEV-A are connected through a subsea pipeline. The Betty field is interconnected with three other fields by pipeline: with the Bokor Field for export of HHP, HP and LP gas (HP and LP pipelines are currently not in service); with the Baronia Field for export of gas from SEP-A Gross liquids are sent from BEP-A to MCOT via the Bakau Field.

SCOPE OF WORK

Sanggul Emas job scope include the Process, Mechanical Design, Material Supply, Manufacture, Inspection, Testing, Painting, Export Protection, Preservation, Process Performance Guarantee & Mechanical Warranty, Shipment and Delivery of:

  • HP Flare Tip (A-6220) DN 400
  • LP Flare Tip (A-6250) DN150
  • Flare Ignition Package (A-6230)
  • Flare Ignition Control Panel (LCP-6230)
  • Propane Bottles Rack (A-6240)

 

List of projects
Customer
SAPURA / PETRONAS CARIGALI SDN. BHD
Industry
Oil and Gas
Project
BOKOR-BETTY
Location
Bintulu Sarawak
Medium
FUEL GAS/ AIR
Brand
Flair

PROJECT DESCRIPTION

The Betty Field is located within the Baram Delta in the South China Sea, about 40km North West of Lutong, Miri, Sarawak.The equity of the field is shared between PCSB and SSS, with PCSB as Operator.

The Betty existing infrastructure comprises three (3) platforms: one (1) Drilling and Production Platform (BEDP-A), a Separation and Liquid Handling Platform (SEP-A) and a Remote Vent Platform (BEV-A). BEDP-A and BEP-A are interconnected by a bridge whereas BEP-A and BEV-A are connected through a subsea pipeline. The Betty field is interconnected with three other fields by pipeline: with the Bokor Field for export of HHP, HP and LP gas (HP and LP pipelines are currently not in service); with the Baronia Field for export of gas from SEP-A Gross liquids are sent from BEP-A to MCOT via the Bakau Field.

The Betty HP wells will flow to the HP separator (V-100) and the gas outlet line from this separator is currently routed to the 18" pipeline pig launcher for export directly to BNG-B at 350psig discharge pressure combined with Laila production to BNG-B. Total HP export to Baronia is restricted to a total of 40MMsfcd due to constraint on ullage availability at BNG-B gas compression facilities, BARDEGG1.

The Laila facility is to facilitate Laila gas handling at BEDP-A. Laila Full Well Stream (FWS) from Laila Wellhead Platform is routed to Laila Slug Catcher (V-1600) for separation. Condensate is combined with Betty production at HP separator (V-100) at SEP-A Gas is routed to BNG-B via PL-355. Laila Gas Jumper Line is connected at the HHP-Separator V-500 gas outlet.

The main objective of Betty Redevelopment (NFA Safeguarding) is to perform the following modifications at SEP-A and BEDP-A to compliment Bokor Central Processing Platform (BOCPP) once it is live.

SCOPE OF WORK

Sanggul Emas job scope include the Process, Mechanical Design, Material Supply, Manufacture, Inspection, Testing, Painting, Export Protection, Preservation, Process Performance Guarantee & Mechanical Warranty, Shipment and Delivery of:

  • HP Flare Tip (A-6220) DN 400
  • LP Flare Tip (A-6250) DN150
  • Flare Ignition Package (A-6230)
  • Flare Ignition Control Panel (LCP-6230)
  • Propane Bottles Rack (A-6240)